Axo Metals Targets First Gold on the Pad in Late 2027
Mining Network Oct 2, 2026 14:25
Summary
A roughly C$7 million all-stock purchase handed Axo Metals a permitted past-producing gold site that is already about 70% built.
The guest says permitting, not geology, stalled the project: he got SEMARNAT approval in six months, versus one to one-and-a-half years typical.
Engineering finishes in 2026, construction starts early 2027, and first gold is stacked on the pad in late 2027.
Step-out drilling 800 metres beyond the resource cut 47 metres of oxide at 1.4 g/t gold, and oxide growth is the cheapest path.
A PEA lands early 2027; the guest expects debt funding for a build in the tens of millions, with oxide gold self-funding a later mill.
Key points on Gogold Resources
- The guest lists GoGold among three group companies, with Silver Tiger and Axo Metals, that have each had a project permit approved within the last ten months, and cites that record as the group's Mexico permitting expertise.
Key points on Silver Tiger Metals
- The guest cites Silver Tiger as the first of three group companies to have had a permit approved within the last ten months, ahead of GoGold and Axo Metals.
Jonathan Egilo's takeaways
- Top takeaway Egilo argues Axo Metals' competitive advantage is Mexico permitting execution, the ability to buy stalled but high-quality projects and unblock them; he notes all three group companies have received permits in the last ten months.
- He frames the San Antonio deal as resurfacing value in an asset that simply needed a change of hands, structured all-stock so Osisko Gold Group participates in the restart rather than cashing out.
- He claims a six-month permitting timeline against the one to one-and-a-half year norm most developers plan around, which lets Axo run engineering early and shortens the overall schedule to construction.
- He argues the initial oxide phase of roughly 40,000-50,000 ounces a year should generate enough early cash flow to self-fund the later sulphide mill and lift production to 100,000 ounces a year or more.
- He is measured on sulphide metallurgy, saying existing studies point to about 90% recovery in a standard agitated leach but that flotation has not been tested yet and remains an optimisation avenue.